Boost 80

Hotel Nomad France

This project demonstrates how a tower crane can operate on a limited grid connection (32A–63A) through the intelligent use of battery buffering.

The challenge

During the construction of the new Hotel Nomad, near Dijon station, Eiffage was confronted with a severely limited grid connection.

Only a "tarif bleu" grid connection was available at the site.
A heavier "tarif jaune" connection was not possible within the project planning.

This limited connection was insufficient to directly power the site and the tower crane (Liebherr 132 EC-H 8).
A traditional solution using diesel generators would have entailed additional costs, noise pollution, and operational complexity, which are undesirable in an urban environment.

The challenge was clear:
reliable power for the tower crane, without a heavy grid connection and without downtime.

The goal

Eiffage sought a solution that:

  • The tower crane could be supplied with power continuously and safely.
  • Could operate on the basis of a limited grid connection
  • Plug & play ready to use, without complex installation
  • Quiet and low-emission operation, suitable for an urban construction site
  • Complete operational certainty provided for yard planning

The solution

Sodemat opted for the Neargrid Boost 80.

The Neargrid Boost served as a local microgrid solution on the construction site:

  • The limited power connection was used to continuously recharge the battery.
  • The Neargrid Boost supplied the necessary peak power to the tower crane.
  • Voltage quality and power peaks were fully buffered and stabilized.
  • The tower crane could rotate as if it had a heavy power connection.

Technical configuration:

  • Product: Neargrid Boost 80
  • Incoming power supply: limited grid connection (“tarif bleu”)
  • Application: Liebherr 132 EC-H 8 tower crane

The installation was completely plug & play and quickly operational, without impacting the site schedule.

The result

Thanks to the efforts of Neargrid:

  • Could the tower crane continue to operate fully electrically and reliably?
  • Was there no need for a heavier grid connection?
  • Was diesel completely avoided for this application?
  • Did the shipyard remain quiet, low-emission, and operational?
  • Did Eiffage not face a risk of downtime due to capacity constraints?

The Neargrid Boost proved once again that even with limited grid capacity, a construction project can continue to run smoothly without compromising reliability.

Date

December 2022

Location

Dijon, France

cranes

Liebherr 132EC-H

Grid connection

32 A - 3f - 400 V

No items found.
By clicking "Accept All Cookies", you agree to the storing of cookies on your device to enhance site navigation, analyze site usage, and assist in our marketing efforts. View our Privacy Policy for more information.