
Boost
Parking tower UZ Gent
Three heavy tower cranes, one limited connection, zero emissions.
The challenge
For the construction of the new parking tower on the UZ Gent campus, Wyckaert needed a reliable, quiet and emission-free energy supply for three large tower cranes:
- Potain MD689 M40 - 40 tons - 75 kW hoist motor → ~120 kVA peak
- 2 × WOLFF 7032.12 Clear - 12 tons - 45 kW hoist motor → ~80 kVA peak per crane
Together good for a theoretical peak demand of +280 kVA when the cranes are running simultaneously.
The available 63A connection (≈ 43 kVA continuous) was at a considerable distance from the crane setups.
A conventional approach would have undesirable consequences:
- Very heavy cables → expensive, difficult to handle, hardly reusable
- Diesel generators → noise, emissions, high fuel consumption, additional maintenance
- Medium-voltage cabin → expensive, slow, infrastructure intensive
Wyckaert sought a solution that is powerful, emission-free and 100% reliable without infrastructure-heavy interventions.
The goal
Running the three tower cranes simultaneously electrically:
- without heavy cabling
- without temporary medium-voltage cabin
- without diesel generators
and within the limited 63A grid connection
With guaranteed stability, silence and zero-emission operation
The solution
Wyckaert, in partnership with Neargrid, chose a Boost 200 kVA site battery, an intelligent microgrid unit that relieves the grid and provides peak power when the cranes need it.
How the configuration works :
Power supply via 63A - 400 V → ± 43 kVA continuously available
During lifting and slewing peaks, the Boost delivers up to 400 kVA, more than enough to run all three tower cranes simultaneously
The battery forms a stable microgrid → no voltage drop, no shutdowns, no silent charges
No need for expensive cable bundles or additional infrastructure
The result
The Boost configuration provides a quiet, emission-free and highly stable power supply for three heavily loaded cranes with only a light mains connection.
The project proves that a complex yard can run entirely electric:
- 0 liters of diesel
- No CO₂ and NOx emissions
- No noise in an environment where nuisance is not acceptable
- No grid reinforcement required
- No downtime risk thanks to automatic peak-shaving
- Lower total cost of operation and minimal infrastructure work
The construction of the parking tower thus becomes a reference project in emission-free construction: powerful performance with minimal connection and maximum reliability.

Date
December 2023
Location
Ghent, Belgium
cranes
Potain MD689 M40, 2 x Wolff 7032.12
Grid connection
63 A - 3f - 400 V


